You are being directed to ZacksTrade, a division of LBMZ Securities and licensed broker-dealer. ZacksTrade and Zacks.com are separate companies. The web link between the two companies is not a solicitation or offer to invest in a particular security or type of security. ZacksTrade does not endorse or adopt any particular investment strategy, any analyst opinion/rating/report or any approach to evaluating individual securities.
If you wish to go to ZacksTrade, click OK. If you do not, click Cancel.
Scana's Unit Files Petition to Modify Capital Cost Schedule
Read MoreHide Full Article
Scana Corporation’s affiliate, South Carolina Electric & Gas Company (“SCE&G”), has filed a petition with the Public Service Commission of South Carolina (SCPSC).
According to the filing, the subsidiary has sought permission to modify its capital cost schedule along with the construction milestone schedule for V.C. Summer Units 2 and 3, the two Westinghouse AP1000 nuclear plants being constructed at the V.C. Summer Station in Jenkinsville, SC.
The petition also includes SCE&G’s notification to the Westinghouse that it will select the Fixed Price Option under the Oct 2015 Amended Engineering, Procurement, and Construction (EPC) contract, subject to formal agreement by Santee Cooper and consent of the SCPSC.
Once this exclusive and binding option takes effect, it will modify the EPC Contract to fix, as of Jun 30, 2015, almost all the costs to be paid for the remaining duration of the V.C. Summer Station project.
Per the petition, the construction schedule shows a definite considerable completion date for Unit 2 of Aug 2019 and a definite considerable completion date for Unit 3 of Aug 2020. These dates were put down by Westinghouse in the Oct 2015 Amended EPC Contract.
After the Amended EPC Contract was signed, Westinghouse appointed Fluor as the subcontracted construction manager for the project. The petition also reveals the increase in SCE&G’s total project costs of about $852 million over the $6.827 billion permitted by the SCPSC in Order No. 2015-661. This comprises about $505 million that is directly linked to the fixed price option. Currently, the total project cost has been approximated at about $7.679 billion, which is inclusive of owner’s cost, transmission, escalation and allowance for funds used during construction.
Currently, Scana Corp carries a Zacks Rank #4 (Sell). Some better-ranked stocks in the oil and gas sector include CVR Refining, LP , Sasol Ltd. (SSL - Free Report) and Braskem S.A. (BAK - Free Report) . All these stocks sport a Zacks Rank #1 (Strong Buy).
Want the latest recommendations from Zacks Investment Research? Today, you can download 7 Best Stocks for the Next 30 Days. Click to get this free report >>
See More Zacks Research for These Tickers
Normally $25 each - click below to receive one report FREE:
Image: Bigstock
Scana's Unit Files Petition to Modify Capital Cost Schedule
Scana Corporation’s affiliate, South Carolina Electric & Gas Company (“SCE&G”), has filed a petition with the Public Service Commission of South Carolina (SCPSC).
According to the filing, the subsidiary has sought permission to modify its capital cost schedule along with the construction milestone schedule for V.C. Summer Units 2 and 3, the two Westinghouse AP1000 nuclear plants being constructed at the V.C. Summer Station in Jenkinsville, SC.
The petition also includes SCE&G’s notification to the Westinghouse that it will select the Fixed Price Option under the Oct 2015 Amended Engineering, Procurement, and Construction (EPC) contract, subject to formal agreement by Santee Cooper and consent of the SCPSC.
Once this exclusive and binding option takes effect, it will modify the EPC Contract to fix, as of Jun 30, 2015, almost all the costs to be paid for the remaining duration of the V.C. Summer Station project.
Per the petition, the construction schedule shows a definite considerable completion date for Unit 2 of Aug 2019 and a definite considerable completion date for Unit 3 of Aug 2020. These dates were put down by Westinghouse in the Oct 2015 Amended EPC Contract.
After the Amended EPC Contract was signed, Westinghouse appointed Fluor as the subcontracted construction manager for the project. The petition also reveals the increase in SCE&G’s total project costs of about $852 million over the $6.827 billion permitted by the SCPSC in Order No. 2015-661. This comprises about $505 million that is directly linked to the fixed price option. Currently, the total project cost has been approximated at about $7.679 billion, which is inclusive of owner’s cost, transmission, escalation and allowance for funds used during construction.